Romania-Hungary gas interconnection – not enough demand for capacity increse

The tender for the increase of the Romania-Hungary interconnector’s capacity, intended to serve the second stage of BRHA gas pipeline project, supposed to link the Black Sea offshore projects with Central Europe, was launched in 2017. Data collected in recently concluded open tender for allocating the additional transport capacity at gas interconnection between Romania and Hungary indicates that there is not enough demand for increasing the capacity of the gas interconnector along the BRHA gas pipeline route from 1.75 billion cubic meters per year to 4.4 billion cubic meters per year.

Although insufficient for justifying the investment, the capacity allocations on the Romania-Hungary direction were a few orders of magnitude larger than those on the reverse direction, of importing gas from Hungary to Romania. The situation is very surprising, because, last year, more than half of the total Romanian gas imports from Russia came via Hungary.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...

Romania becomes Southeast Europe’s battery-financing laboratory

Romania is moving beyond announcing battery projects and beginning to demonstrate how large-scale storage can actually be financed. August produced some of the clearest evidence yet. Econergy’s Părău 2 project secured a financing package of approximately €229 million from six banks and financial institutions. The...
Supported byVirtu Energy