Romania: High concentration of wind farms in eastern part of the country

Until the ongoing projects for increased the network’s capacity are completed no new electricity generation capacities could be licensed for connection to the network in southeastern Romania (Dobrogea and surrounding regions), said Romanian electricity transmission system operator Transelectrica.

The statement was not specific in regard to the type of generation capacities, but it is particularly relevant for the renewable energy (solar and especially wind) projects that were already launched or are planned in the region, as part of a new wave of such investments after the slowdown prompted by the change in regulations around 2013. Another reason is slow implementation of Transelectrica’s projects in this part of the country, i.e. some investments launched 18 years ago have not been yet completed.

However, the statement from Transelectrica states that things are not much better in the other region. In the northeastern part of the country, the estimate is that new generation facilities can still be connected to the network, but technical connection permits are already issued for the available capacity of the transmission network. Any new applications will require investments in the network’s upgrades.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania’s €1.2 billion Mintia gas plant enters commissioning ahead of grid connection

Romania’s 1.7 GW Mintia gas-fired power project has reached a major commissioning milestone with the first turbine ignition, bringing one of Southeast Europe’s largest new thermal generation investments closer to commercial operation. The development comes as Romania faces nuclear...

OMV Petrom refining margin rises while upstream output and gas sales fall

Third-quarter refining margin and refinery operating levels OMV Petrom reported a sharp increase in its third-quarter indicator refining margin, with the refining benchmark reaching $41.75 per barrel. The figure compares with $14.02 a year earlier and $22.67 in the second...

Mintia gas-fired plant starts turbine testing as commissioning advances

Romania’s Mintia gas-fired power project has entered a further commissioning stage after its first turbine operated on natural gas on October 8. The next steps require additional testing and synchronisation with the national transmission network before deliveries can begin....
Supported byVirtu Energy