Romania: High concentration of wind farms in eastern part of the country

Until the ongoing projects for increased the network’s capacity are completed no new electricity generation capacities could be licensed for connection to the network in southeastern Romania (Dobrogea and surrounding regions), said Romanian electricity transmission system operator Transelectrica.

The statement was not specific in regard to the type of generation capacities, but it is particularly relevant for the renewable energy (solar and especially wind) projects that were already launched or are planned in the region, as part of a new wave of such investments after the slowdown prompted by the change in regulations around 2013. Another reason is slow implementation of Transelectrica’s projects in this part of the country, i.e. some investments launched 18 years ago have not been yet completed.

However, the statement from Transelectrica states that things are not much better in the other region. In the northeastern part of the country, the estimate is that new generation facilities can still be connected to the network, but technical connection permits are already issued for the available capacity of the transmission network. Any new applications will require investments in the network’s upgrades.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...
Supported byVirtu Energy