Romania: BRHA last compressor station commissioned by Transgaz

The compressor station is the third and last within the first phase of the Bulgaria-Romania-Hungary-Austria (BRHA) pipeline project in Romania. Romanian natural gas transmission system operator Transgaz has commissioned the Bibesti gas compressor station, which is a part of the first phase of the project for the construction of BRHA gas pipeline.

Transgaz invested 39 million euros in the construction of the station. The Romanian section of the pipeline is expected to be completed in November.

Last October, Transgaz commissioned two gas compressor station along the BRHA route – Podisor and Jupa. The company said that the Romanian section of BRHA gas pipeline will not be completed by the end of 2019 as it was initially planned, but instead in December 2020. The statement from the company said that with all the efforts made by Transgaz for the realization of the BRHA Phase I project, during the implementation of the project, problems were encountered which, cumulatively, affected the full implementation of the project within the assumed period. The issues are mainly arising from the conduct of the tender procedures, the completion and improvement of the legislative framework, the identification of archaeological sites, meteorological – adverse conditions that have manifested over long periods of time, the extension of negotiations with some land owners/users, and a large number of changes that appeared during the implementation of the works. In June 2018, Transgaz has started the construction of the first phase of BRHA gas pipeline. The first phase of the project will include the construction of Podisor-Recas gas pipeline. The total amount of funds estimated for the first phase is 478.6 million euros. Each of two stations will be equipped with two compressor units (one active and one redundant) and will have the technical capability to enable bidirectional gas flows. Some 40 % of the costs of the project are covered by the European Union, through a grant worth 179 million euros. Initial completion date of the first phase of BRHA gas pipeline was December 2019 and it will enable gas flows from Romania to Hungary and Bulgaria.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania seeks to extend emergency power controls as supply risks persist

Romania is seeking to extend its emergency electricity-market powers through October 31, maintaining the option to restrict exports or limit industrial consumption if prolonged nuclear and hydropower constraints threaten security of supply. Under the proposed extension, transmission system operator Transelectrica...

Romania transforms telecom backup batteries into virtual power plant

Romania is testing whether thousands of backup batteries installed at telecommunications sites can be transformed from emergency infrastructure into a distributed virtual power plant capable of generating revenue in electricity flexibility markets. Huawei Romania, Bamboo Energy and Flexumers are developing...

Rezolv Energy commissions 192 MW first phase of Vifor wind farm in Romania

Vifor project capacity and turbine configuration Rezolv Energy has commissioned the 192 MW first phase of its Vifor wind farm in Romania. The project is located in Buzău County. The first phase uses 30 Vestas V162 EnVentus turbines, each rated...
Supported byVirtu Energy