Proposal Date: 17.February.2011
Proposed Beginning: 1.June.2012
Planned Duration (in months): 24
Project Value: US $ 63.50500 million (50,000,000.00 EUR)

Project Status: Proposal

Reference Number: PENE2174

Background and Justification: Public Enterprise Electric power industry of Serbia (PE EPS) was established by the Decision of the Government of Serbia which entered into force on 1 July 2005 (100% ownership of the Republic of Serbia).

Vertically integrated enterprise comprises of 11 corporate enterprises. (EPS cannot manage its facilities at Kosovo and Metohija as of June 1999): facilities for electricity generation, facilities for coal production, processing and transport, electricity distribution

Installed capacity of EPS power plants amounts to the total of 8,359 MW, as follows:

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia power prices rise as regional markets retreat from Tuesday’s spike

Serbia’s day-ahead electricity price rose by €18.2/MWh to €195.99/MWh for Wednesday delivery, moving in the opposite direction to sharp declines across most neighbouring markets and narrowing the gap with Hungary to just €2.99/MWh. Hungary’s HUPX benchmark fell by €34.9/MWh to...

EMS begins Bajina Bašta 220 kV to 400 kV upgrade for Trans-Balkan Corridor

Serbian transmission system operator EMS has started upgrading the Bajina Bašta substation from 220 kV to 400 kV, supporting the western segment of the Trans-Balkan Corridor. The project covers the current corridor section valued at around €115 million. The...

Fortis and Inelso to build 30 MW solar with battery storage in Vojvodina

Fortis Energy and Inelso Energy Systems plan to invest about €25.5 million in a 30 MW solar project with battery storage in Serbia’s Vojvodina region. The development is described as ready to build. The project is expected to proceed...
Supported byVirtu Energy