Paks II construction advances amid Hungary financing and contract review

Construction on Paks II, Hungary’s 2,400 MW nuclear project, is continuing as the government reviews elements of the project’s contractual and financial structure. The review adds uncertainty around one of Central Europe’s largest energy investments. Work progress is reported across both civil works and component manufacturing.

Reactor-building works for Units 5 and 6

Preparations for the reactor-building foundation at Unit 5 are more than 80% complete. The stage follows the pouring of more than 18,000 cubic metres of concrete. Remaining foundation works are expected to be completed before winter.

Excavation of the nuclear island for Unit 6 is also progressing. Preparations for first concrete are planned before the end of 2026. These timelines are part of the parallel schedule for different parts of the site.

Manufacturing progress and international supply chain

Rosatom has started producing equipment for both VVER-1200 reactors. A 730-tonne core catcher for the first unit was delivered to the Paks site in 2024. Manufacturing activity is described as moving ahead alongside construction.

The supply chain includes companies from France, the US, Germany, Austria, Switzerland, the Netherlands, the Czech Republic, Slovakia and Turkey. Alstom began manufacturing turbines at its Belfort facility in April 2025.

Financing structure and potential renegotiation risks

The financing architecture remains a sensitive issue for the project. Paks II is supported by a Russian state loan of up to €10bn. The government’s ongoing review focuses on parts of the contractual and financial structure.

If major changes are made to existing contracts or if the principal contractor is replaced, renegotiation of that financing could be required. Such renegotiation could potentially delay completion.

Cooling-water resilience amid low Danube levels

Environmental resilience has become an additional consideration for operations planning. Exceptionally low Danube levels have raised questions about cooling-water availability. The issue includes whether further measures are needed to strengthen operation during drought conditions.

More substantial design changes, including closed-loop cooling, would add cost and could affect the schedule. Budapest is weighing those longer-term concerns against the high cost of changing a project already deep into construction.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Hungary: HUPX day-ahead power prices jump 24% in August as trading volumes rise

Hungarian day-ahead electricity prices rose significantly in August, while trading volumes increased both month on month and year on year, reflecting stronger activity on the country’s wholesale power market. The average HUPX day-ahead baseload price reached €152.17/MWh, marking a 24.4%...

Paks II commissioning timeline uncertainty as Hungary’s nuclear replacement window tightens

Paks II schedule risk extends into 2035 Hungary’s Paks II nuclear expansion could see completion pushed to 2035, according to an internal construction timetable cited in a report. The same source indicates the project could be delayed until 2035, narrowing...

Hungary tenders 702 MVA grid capacity for new wind projects

Hungary has launched a tender for 702 MVA of grid connection capacity reserved for new wind projects. The allocation is intended to reopen access to grid capacity after a period in which wind development remained largely frozen while solar...
Supported byVirtu Energy