Romgaz targets first power from Iernut gas plant before year-end

Planned start-up of 430 MW Iernut unit

Romgaz is targeting first electricity from its long-delayed Iernut gas-fired power station before the end of 2026. The project has a stated capacity of 430 MW, with the company aiming to bring the plant online as Romania’s power system absorbs more wind and solar generation. Romgaz’s timetable is linked to the availability of additional flexible capacity in the market.

Construction timeline and procurement changes

Work on Iernut began in 2016, but commissioning was pushed well beyond the original schedule due to contractual disagreements and repeated implementation problems. A government memorandum approved in May eased procurement procedures for remaining works. The change is intended to give Romgaz more flexibility to accelerate completion of the project.

Site activity and grid synchronisation plans

Activity at the Iernut site is expected to increase substantially from 1 September. Romgaz believes the plant could be synchronised with the national grid before year-end. The company has not yet confirmed the date for full commercial operation.

Role in balancing rising renewables and intraday volatility

Iernut’s contribution to the Romanian market is described as being based on flexibility as well as headline generating capacity. The new unit is intended to respond to changes in renewable output rather than run continuously as conventional baseload generation. That balancing function is expected to matter more as Romanian solar, wind, and battery capacity expand and intraday volatility increases.

Generation from existing Iernut assets during build-out

Until the new plant becomes available, Romgaz continues generating electricity from existing Iernut facilities. This includes a 200 MW coal unit operating at full capacity. Production from these assets is set to continue while construction and commissioning of the gas-fired station proceed.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

TDI financing for 58 MW Iratoșu solar plant in western Romania

TDI Renewables has secured €25.5 million in financing from Raiffeisen Bank International for its 58 MW Iratoșu solar power plant in western Romania. The project is located in Arad county and is part of a broader development programme that...

Nuclearelectrica revises 2026 outlook as Cernavoda outages drive replacement power costs

Romanian nuclear producer Nuclearelectrica has reduced its forecast for 2026 net profit by 42.9% to €221 million. The company attributed the change to prolonged outages at Cernavoda, which have lowered electricity sales and required purchases of replacement power. Revised...

Romania extends 25% diesel excise reduction until Oct. 31

Romania will keep a 25% reduction in diesel excise duty until Oct. 31, extending temporary relief for transport operators and other businesses. The decision follows a period in which international fuel-market prices have risen faster than domestic pump prices....
Supported byVirtu Energy