Montenegro: Construction progresses on Gvozd wind farm, a major step in renewable energy transition

Concrete pouring has begun for the first of eight foundations that will support the wind turbines of the Gvozd wind farm, located near Nikšić. This ambitious project, with an estimated value of around 82 million euros, stands among the most significant energy developments currently underway in Montenegro. The state-owned power utility EPCG is the investor behind the project, while the construction is being carried out by Bemax, a company with prior experience in wind energy infrastructure, having worked on the Krnovo and Mozura wind farms.

The construction schedule is designed for swift execution. By the end of this month, three more turbine foundations are expected to be completed, with the final four planned for early September. Simultaneously, preparations to connect the turbines to the power grid will begin in July. The entire project is set to be finalized by May 2026. Positioned in the hilly region between Nikšić and Šavnik, near the existing Krnovo wind farm, Gvozd will feature eight turbines, each mounted on a foundation with a 25-meter diameter.

The Gvozd wind farm is not only an important infrastructure project but also a strategic move in Montenegro’s transition to renewable energy. With eight turbines planned in the first phase and the potential to expand by four more, supported by the construction of necessary platforms and infrastructure, the project will enhance the country’s energy independence. The 18-month construction timeline, which began in December 2024, is progressing steadily. To date, more than nine out of ten preliminary tasks have already been completed.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Gvozd II wind expansion set for spring 2027 as EPCG complex reaches 76 MW

Montenegro is targeting spring 2027 for the commissioning of Gvozd II, as state utility EPCG expands its wind portfolio. The project is expected to bring the overall Gvozd complex to 76 MW. Construction activity is progressing on one of...

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...
Supported byVirtu Energy