Slovenia’s Krško nuclear power plant has returned its reactor to 100 per cent power following cooler weather, rainfall and improving conditions on the Sava River. The changes eased environmental restrictions that had constrained production since early August.

Derating steps as river flows and temperatures changed

The plant initially cut output to 80 per cent when very low river flows coincided with elevated water temperatures. As conditions improved, generation was increased to 90 per cent. On the evening of 18 August, the unit returned to full reactor power.

Grid deliveries remain below typical levels

Electricity supplied to the grid has not yet fully returned to normal. During the afternoon, the plant was delivering approximately 660 MW, compared with more than 700 MW under typical operating conditions.

A portion of the shortfall is linked to continued use of the cooling-tower system. Some of the plant’s own electricity is being consumed to operate cooling infrastructure, which reduces dependence on Sava River water while helping keep operations within environmental limits.

Hydrology-linked nuclear availability in regional markets

The episode highlights a direct connection between extreme summer hydrological conditions and nuclear availability in the region. Krško is described as a major source of stable generation for both Slovenia and Croatia. Partial derating is therefore relevant for cross-border balances and wholesale prices.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Krško nuclear plant generates 487,438 MWh in September 2026, misses target

The Krško nuclear power plant, jointly owned by Slovenia and Croatia, produced 487,438 MWh of net electricity in September 2026. Output was 1.53% below the plant’s monthly production target for the month. The reported shortfall followed a plan to...

Enery begins Jezerce hybrid solar-battery build with €88/MWh municipal offtake

Vienna-based renewable energy group Enery has started construction of a hybrid solar and battery facility in Slovenia at the Jezerce project near Divača. The installation combines 7.68 MW of photovoltaic capacity with 12 MWh of electricity storage. Project location...

Slovenia’s industrial power-sharing model delivers measurable savings as market scales

Slovenia’s electricity-sharing market is beginning to deliver measurable savings for industrial consumers, strengthening the case for an emerging energy-service model focused on allocating existing renewable generation more efficiently rather than building additional generation assets. Slovenian energy technology company SunContract said...
Supported byVirtu Energy