Many applications for network connection of small-scale renewable projects in Greece are currently being turned down as the network capacity in some regions has reached its limit.

According to data published by electricity distribution system operator DEDDIE, medium-voltage electricity network is unable to accept more connections in 40 % of the country, including western Macedonia.

This issue is primarily related to small-scale renewable energy projects. Bigger projects are connected to the high-voltage network, managed by the transmission system operator ADMIE.

In February, DEDDIE’s parent company PPC signed an agreement for a 100 million euros loan from the European Investment Bank (EIB) aimed to expand the electricity distribution network across the mainland and islands so as to meet rising demand and improve the security of electricity supply.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy