Supported byClarion Energy
HomeElectricityGreece moves forward...

Greece moves forward with long-delayed Mesochora hydropower plant

The Greek Ministry of Environment and Energy has confirmed that the long-delayed Mesochora hydropower plant in Trikala will finally advance, bringing an end to more than two decades of legal battles and halted construction. Although the project was officially revived in 2021–2022, decisive action is only now being taken to move it toward completion.

A new agreement has been signed with the Public Power Corporation (PPC), which developed the facility and will operate it once finished. Under the agreement, PPC will oversee and finance the remaining studies required to finalize the 161.6 MW project. The most critical element is the resettlement plan for residents of the Mesochora settlement—a longstanding obstacle that has prevented the plant from being commissioned. PPC will carry out the relocation work at a cost of 1.31 million euros, while the Government has reiterated that all affected households will be safely resettled and fully compensated.

Construction of the dam on the upper Acheloos River began in 1986 and was structurally completed by 2001. Since then, lawsuits and appeals by local communities and environmental groups have prevented the project from entering operation. More than 300 million euros have been spent to date—equivalent to nearly 500 million euros in today’s value.

The Ministry has established a dedicated task force to accelerate the remaining procedures, with the goal of restarting final construction works by the end of 2026. Expropriation of the remaining land parcels will proceed in parallel to ensure the dam and supporting infrastructure can operate as intended.

Once commissioned, the Mesochora hydropower plant is expected to generate around 360 GWh of electricity annually. In addition to contributing a significant volume of renewable energy to Greece’s power mix and aligning with the country’s updated National Energy and Climate Plan, the facility is projected to strengthen grid-balancing capabilities amid rapid growth in solar and wind production.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy