Greek natural gas transmission system operator DESFA said that a market test for gas interconnection with North Macedonia will be
launched in March, following the completion of the related public consultation procedure in early February.

In late 2021, DESFA signed a 25 million euros loan agreement with the European Investment Bank (EIB) for the construction of Greek section of the pipeline.

The Greek section, budgeted at 67 million euros, is planned to run from Nea Mesimvria, on the western outskirts of Thessaloniki, to the Evzoni area on the northern border with North Macedonia.

The EIB also approved 28.9 million euros loan agreement for the Macedonian section of the pipeline, in addition to 12.4 million euros loan
from the Western Balkans Investment Framework (WBIF).

Overall cost of Greece-North Macedonia gas interconnection, a 123 kilometers long pipeline, is estimated to 110 million euros.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greek regulator probes whether solar cuts followed negative wholesale prices

RAAEY review of August midday solar output drops Greece’s energy regulator, RAAEY, is investigating whether solar producers deliberately reduced generation during periods of negative wholesale prices in August. The review covers several hours between Aug. 17 and Aug. 23. During...

Greece €5 billion energy package to cut final electricity prices by 30%

Prime Minister Kyriakos Mitsotakis presented a programme at the Thessaloniki International Fair. The plan targets a reduction of final electricity prices by about 30% by 2029. It is set at a total envelope of €5 billion and is designed...

OKTA commissions 3 MW battery storage with North Macedonia 12 MW solar plant