Greece: Grid injection cuts to sharply increase due to slower integration of energy storage units

Grid-injection cuts of renewable energy production offered to the grid will increase considerably over the next couple of years as a result of a greater presence of operating renewables combined with relatively slower incorporation of energy storage units to the grid, formulas applied to calculate prospective cuts have shown.

RES grid-injection cuts totalled 228 GW in 2023 but are expected to more than double this year, reaching over 500 GW, before skyrocketing to more than 1.5 TWh in 2025, according to projections, which is unfavourable news for RES producers and consumers, who would both benefit if this output were fully utilized.

A first wave of energy storage units is not expected to be linked to the grid until early 2026, meaning grid operators will have no choice but to dump excess renewable energy production made available over the next two years.

At present, RES facilities in operation offer a total production capacity of between 11.5 and 12 GW, while the market penetration rate of new units entering the grid totals 2 GW, annually, and consists mostly of PVs.

At this rate, RES facility additions to the country’s grid are expected to total roughly 16 GW by 2026.

Over this period, electricity demand is projected to grow modestly, from 49 TWh in 2023 to 49.5 TWh in 2024 and 51 TWh in 2025. Such demand levels will be insufficient to fully absorb the additional RES output expected to be made available over the same period, energypress.eu reports.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Greece approves €2.3bn programme for island grids, renewables and storage

Greece has secured approval for a €2.3 billion programme aimed at decarbonising its islands, with Athens directing more than €2 billion towards electricity interconnections, renewable generation and storage as it accelerates the replacement of oil-fired power. The approval was...

Metlen signs 10-year PPA for 12 MW Greek solar supply to Coca-Cola Tria Epsilon

Metlen Energy & Metals has signed a 10-year power purchase agreement to supply Coca-Cola Tria Epsilon with electricity from a new 12 MW solar project in Greece. The agreement is structured as a bilateral contract for long-term renewable power...

Greece wind buildout set to miss 2030 target despite faster 2026 additions

Greece accelerated wind-power construction in the first half of 2026, but projections indicate the country is still set to miss its 2030 capacity target. The outlook is based on figures cited in a document . Developers commissioned 321 MW...
Supported byVirtu Energy