Enercon to deliver 7-MW turbines for Qair’s Cobadin I wind farm in Romania

Enercon will supply its E-175 EP5 E2 turbine platform for Qair’s Cobadin I wind farm in Romania. The project is described as a 50-MW development under the first phase of the Cobadin complex. The deployment marks the first time the E-175 EP5 E2 platform will be used in Romania.

Turbine specifications for Cobadin I

Enercon will provide seven turbines rated at 7 MW each. The machines are configured with 175-metre rotor diameters mounted on 112-metre steel towers. Enercon is also scheduled to provide long-term servicing for the installation.

Timeline and commissioning schedule

Installation for the Cobadin I turbines is scheduled to begin in July 2027. The first turbine is expected to be commissioned by the end of August 2027. The delivery and commissioning timetable is linked to the start of works planned for that summer period.

Cobadin complex structure and CfD arrangements

Cobadin is planned as two phases of 50 MW, bringing the overall complex capacity to 100 MW. Cobadin I secured a Romanian Contract for Difference in January 2025. Qair later obtained a separate CfD covering the second phase of the development.

The agreement is stated to be the first Romanian wind project jointly developed by Enercon and Qair. It provides Enercon with an entry point for its latest high-capacity onshore turbine platform into a market supported by CfD-backed projects. The information is presented in connection with a new wind-investment cycle supported by those CfD awards.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...
Supported byVirtu Energy