Croatia: The Testing of the unit C of TPP Sisak starts

Croatia power utility HEP takes over the TPP Sisak unit C at the end of this year or early next year, it confirmed director of TPP Sisak Matija Horžić .
“All construction and assembly works are completed. The construction lasted more than three years because of the public procurement, production equipment, harmonization of domestic contractors and foreign supervisors. Testing of certain plant parts and their putting into operation are starting now. The download process will be done no later than by the end of this year or early next year”, said Horzic.

The third unit of 230 MW of electricity and 50 MW of thermal energy is financed by offsetting the clearing debt of the Russian Federation to Croatia in the amount of 188 MEUR. Gas steam turbine is made in Russia under Siemens license.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Banatski Dvor expansion delays deepen Serbia’s reliance on Hungarian storage

Serbia’s Banatski Dvor underground gas storage expansion is experiencing further slippage, according to project timelines that have moved past the previously targeted end of 2026. The delay increases the need for additional storage capacity outside Serbia. Serbia rents about...

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Hungary granted temporary EU delay on Serbia gas capacity bundling rules

Hungary has received temporary approval from the European Commission to postpone full implementation of EU gas-capacity rules at its border with Serbia until the 2027/2028 gas year. The derogation relates to requirements that cross-border pipeline capacity be offered as...
Supported byVirtu Energy