Bulgaria: Toshiba, Voith and ABB to revitalize Chaira pump-storage hydropower plant

Toshiba Corporation, in collaboration with a consortium comprising the German Voith Group and Swiss ABB, has signed contracts to repair and rehabilitate two units at Bulgaria’s Chaira pump-storage hydropower plant. Toshiba will handle repairs for unit 1, while the Voith-ABB consortium will be responsible for unit 3. The project aims to restore three of the plant’s four units by early 2026, which will generate over 600 MW of electricity in both pumping and storage modes. This is crucial for energy security, balancing the energy network, and integrating renewable energy in the region.

The Chaira plant, the largest pump-storage facility in the Balkans, has been offline since March 2022 following an incident during post-rehabilitation testing. However, unit 2 resumed operation last month after repairs. Additionally, Bulgaria’s National Electricity Company (NEK) has launched a tender for the supply and replacement of generators, turbines, equipment, and control systems for units 1 and 4.

Chaira has an installed capacity of 864 MW in generating mode and 772 MW in pumping mode, using four Toshiba-made Francis pump-turbines. It has been operational since 1995, with rehabilitation efforts beginning in 2019 following an emergency shutdown in 2018.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bulgargaz obtains 10-year wholesale gas licence for Serbia

Bulgargaz, the Bulgarian state-owned gas supplier, has secured a 10-year wholesale gas licence in Serbia. The permit authorises the company to conduct commercial gas trading on the Serbian market. The development extends Bulgargaz’s trading footprint across Southeastern and Central...

Kozloduy unit 5 output cut as Danube levels fall below cooling-water thresholds

Bulgaria’s Kozloduy nuclear power plant has reduced output from unit 5 after exceptionally low Danube levels constrained cooling-water availability. Regulators said the plant remains within safe operating limits. The reduction is linked to river conditions rather than an identified...

Bulgaria competition authority expands Lukoil wholesale fuel pricing investigation

Bulgaria’s competition authority has intensified its examination of the wholesale fuel market, requesting additional cost and pricing information from Lukoil Bulgaria and Lukoil Neftochim Burgas. The request is part of an ongoing probe into how changes in crude-oil prices,...
Supported byVirtu Energy