Bulgaria: Rosatom completed Unit 5 upgrade at NPP Kozloduy

Rosatom Service, subsidiary of Russian stateowned nuclear company Rosatom, issued a statement in which it said that the company has completed the upgrade of unit 5 at Bulgarian nuclear power plant Kozloduy, as a part of the project for lifespan extension of units 5 and 6.

The 360 million euros worth project for the upgrade of NPP Kozloduy’s two 1,000 MW reactors is aimed at the extension of its operational life by additional 30 years, thus avoiding the unpopular increase in electricity prices.

In October 2014, NPP Kozloduy confirmed it had signed the contract for the second phase of the project for extension of the operational life of the unit 5 (1,000 MW) with the consortium of Rosatom Services, Rosenergoatom and EDF. The aim of the contract is the extension of the safe operational of the unit 5 up to 60 years, i.e. by another 30 years. The operational license of unit 5 is due to expire in 2017, while the license for unit 6 is due to expire in 2019.

Originally, NPP Kozloduy had six reactors, but four older 440 MW reactors were shut down in 2007 due to nuclear safety concern of the European Union. The plant currently operates two Soviet-built 1,000 MW reactors, unit 5 and unit 6 which were commissioned in 1987 and 1991 respectively, transmits Serbia-energy.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

SEE power prices ease as imports increase, while Serbia defies regional trend

Southeast European day-ahead electricity prices declined across most markets for Wednesday delivery, narrowing Hungary’s premium over Germany. At the same time, higher gas and carbon costs continued to support firmer forward power prices. Serbia moved against the broader regional trend,...

North Macedonia’s electricity trading jumps 74% as September prices rise

Electricity traded on North Macedonia’s MEMO day-ahead exchange rose 74% year on year to 179.2 GWh in September, pointing to increased participation and growing use of the organised electricity market. Despite the strong annual increase, trading volumes fell 10.3% from...

Serbia plans North Macedonia gas interconnector construction start, aiming Q1 2028

Pipeline scope and early works near Vranjska Banja Serbia is targeting early 2028 completion for its gas interconnector with North Macedonia, with construction planned to start and reach completion in the first quarter of 2028. Initial works near Vranjska Banja...
Supported byVirtu Energy