Bulgaria: NPP Belene claim may trigger arbitration

Bulgarian Minister of Energy Temenuzhka Petkova said that electricity prices will not be increased after last week’s announcement that Bulgaria was ordered to pay 0.55 billion euros for the cancelled NPP Belene project.

Minister Petkova said that National electric Company (NEK) will not bear any financial losses as a result of this ruling. The aforementioned 550 million euros will be used to purchase two nuclear reactors (of which one is completed and the other is under construction) and possibly sell these to a third party, because, according to the Minister, there is a market for such equipment, most likely in Iran or India.

Last week, the International Arbitration Court in Paris has ruled that Bulgaria has to pay 0.55 million euros to Russian company Atomstroyexport (ASE) over the cancelled project for the construction of nuclear power plant Belene. However, ASE claims that the ruling says that Bulgaria has to pay 620 million euros and not 550 million. Initial arbitration demand exceeded one billion euros, transmits Serbia-energy.eu

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Southeast Europe power prices drop on Saturday, but evening peaks stay above €250/MWh

Electricity baseload prices fell by more than 20% across several Southeast European markets for Saturday delivery. Despite the decline, evening prices still rose above €250/MWh, indicating that flexibility remains priced into the most constrained hours. The day-ahead figures show...

Croatia extends winter price support for household electricity, gas and heating

Winter support period and budget allocation Croatia is spending about €170 million to keep household electricity, gas and heating costs below market levels during winter. The programme is designed to shield consumers from wholesale volatility while delaying a return to...

Kapino Polje solar complex expands EPCG generation near Nikšić to about 40 MW

Construction progress on L1, L2 and B1 sections Work has started on the Kapino Polje project near Nikšić, with activity under way on the L1, L2 and B1 sections. The combined scope for these sections represents around 20 MW. Support...
Supported byVirtu Energy