Bosnia and Herzegovina: Ugljevik Power Plant Settles Financial Dispute with Slovenian Partner

The resolution of a significant financial dispute between the RiTE Ugljevik coalmine and thermal power plant and its Slovenian partner, Elektrogospodarstvo Slovenije (EGS), has been achieved through a new agreement valued at approximately 37 million euros. This settlement marks the conclusion of a complex case that had implications for both parties’ operations and financial stability.

Prior to this agreement, the prospect of escalating claims posed a substantial risk, potentially reaching nearly 650 million euros. However, the newly negotiated terms have allowed both entities to withdraw from a looming arbitration process in Washington, thereby mitigating prolonged legal uncertainties that could have adversely affected their operational focus.

The roots of this dispute trace back to earlier rulings which mandated RiTE Ugljevik to compensate EGS for undelivered electricity spanning from 2011 to early 2022, alongside additional compensation for subsequent years. The new agreement stipulates that ongoing electricity production from the plant will continue to be supplied to the Slovenian partner, ensuring compliance with prior commitments.

While previous arrangements had addressed most of the principal debt and compensation, unresolved issues surrounding accrued interest lingered. The final agreement effectively resolves these outstanding components, including a reduction in the initially claimed amounts, thus facilitating a complete closure of the case.

A structured payment plan is already in effect, with initial payments being processed. Concurrently, electricity deliveries to EGS have commenced since early 2024, reflecting adherence to established obligations. The agreement’s stability is reinforced by backing from the parent utility company, ensuring that all terms are enforced effectively.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia and Herzegovina drafts KfW loan for 132 MW Poklečani wind farm

KfW financing draft for Poklečani wind farm Bosnia and Herzegovina has approved a draft financing agreement with German development bank KfW for the 132 MW Poklečani wind farm. The project is described as one of the largest planned renewable-energy investments...

FBiH tenders 1.67 million litres of strategic diesel for Blažuj terminal

Procurement details for strategic diesel stocks The Federation of Bosnia and Herzegovina has launched a procurement for 1.67 million litres of diesel to expand strategic fuel stocks at the Blažuj petroleum terminal near Sarajevo. The contract is valued at approximately...

Bosnia advances €103 million financing for Poklečani wind and Elektrokrajina grid upgrades

Bosnia and Herzegovina has advanced around €103 million of proposed financing covering new wind capacity and distribution-grid upgrades. The package targets both additional generation and constraints in the network that increasingly limit renewable deployment. The Council of Ministers has...
Supported byVirtu Energy