OMV Petrom pushes ahead with €560 million sustainable-fuels complex at Petrobrazi

Romania’s OMV Petrom has advanced construction of a €560 million sustainable-fuels complex at its Petrobrazi refinery, with commissioning targeted for 2028. Construction of the facility began in 2025. Major reactors and processing columns have been installed as part of the buildout. Some equipment has reached heights of up to 60 metres.

Foundation work for the project used about 20,000 cubic metres of concrete. The next phase will focus on completing equipment installation. OMV Petrom plans to connect the new units with the existing refinery and carry out testing and verification before commercial production.

Sustainable aviation fuel and renewable diesel output

The plant is designed to produce approximately 250,000 tonnes of sustainable aviation fuel and renewable diesel annually. Expected feedstocks include vegetable fats and used cooking oil. The development is structured to support production of lower-carbon liquid fuels using these inputs.

Green hydrogen integration and electrolyser capacity

The sustainable-fuels project is integrated with a separate €190 million green-hydrogen programme. Two electrolysers are planned with combined capacity of 55 MW. The hydrogen is intended for use in the production of lower-carbon liquid fuels.

Market positioning and dependencies for returns

The combined investments are intended to reposition Petrobrazi for markets where liquid fuels will remain difficult to replace, particularly aviation and heavy transport. The project also provides OMV Petrom an early position in southeastern Europe’s sustainable-fuels market. Returns are expected to depend on access to affordable feedstock and green electricity. They will also rely on whether premium airlines and fuel suppliers are willing or required to pay for lower-emission products.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Enexus to add 50 MWh battery storage to Romanian solar in Titu

Romanian renewable developer Enexus plans to install 50 MWh of battery storage alongside two solar projects in Titu, Dâmbovița county. The move extends Enexus’s cooperation with LONGi beyond photovoltaic modules. The hybrid configuration will pair solar generation with storage...

PPC moves 60 MW/129 MWh battery toward construction alongside Târgușor wind farm

PPC Renewables is advancing a 60 MW/129 MWh battery project positioned alongside its operating 120 MW Târgușor wind farm, bringing the asset closer to construction. The battery would be colocated with the wind facility in Constanța. The move is...

Romanian forward power clears above €205/MWh as winter risk prices in

Romanian electricity for January 2027 has traded above €205/MWh, indicating that the country’s scarcity premium is being embedded months ahead into winter procurement. The move follows recent trading activity in the forward market rather than being limited to volatile...
Supported byVirtu Energy