Croatian company Kermas Energy will have to pay over 10.5 million euros to Serbian company Omega Plus over the failed project for the construction of Trusina wind farm near Nevesinje.

The two companies established a joint venture Eol Prvi, which has obtained the concession for the 51 MW wind farm, a project worth over 75 million euros. However, the start of the construction was postponed several times and, at the end, the Government of the Republic of Srpska (RS) has terminated the concession agreement with the company. Soon after, the two companies have filed lawsuits, blaming each other for the project’s demise.

Last week, the District Commercial Court in Trebinje ruled that Kermas Energy has to pay 6.3 million euros to Serbian company in the name of compensation for lost profits because it did not fulfill the obligations undertaken by the agreement on the construction and operation of the wind farm signed in 2014.

Furthermore, it has to settle the debt to Omega Plus in the amount of 4.4 million euros on the basis of the shares in the company Eol Prvi, which it transferred to itself, but did not pay.

In October 2012, local company Eol Prvi has obtained 30-year concession contract for the construction of 51 MW wind farm near Nevesinje.

The wind farm is expected to produce some 160 GWh of electricity per year, which would be enough to supply some 40,000 households, while the turbines will be delivered by the Danish Vestas. The wind farm was expected to be completed by the end of 2019, however, the concession agreement was terminated because the concessionaire failed to provide a bank guarantee.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...

EPBiH coal shortages raise risk of further electricity tariff pressure in 2026-2027

EPBiH, the state-owned power utility in Bosnia and Herzegovina, faces renewed electricity-price pressure as coal supply problems contribute to losses. The company could see pressure for another electricity-price increase by late 2026 or early 2027, according to the conditions...

Republika Srpska to raise electricity prices from 2027 amid Ugljevik coal issues

Businesses in Republika Srpska are expected to see higher electricity prices starting in January 2027, with households facing increases from March. The authorities are also seeking to strengthen the power sector’s finances while addressing coal supply problems that could...
Supported byVirtu Energy