Bosnia and Herzegovina: ICSID still haven’t decided on TPP Ugljevik arbitration

The International Center for Settlement of Investment Disputes (ICSID) in Washington still haven’t decided whether it is competent to rule on the arbitration against Bosnia and Herzegovina (BiH) and coalmine and thermal power plant (RiTE) Ugljevik, operated by power utility ERS, filed by Slovenian company Elektrogospodarstvo.
Initially, ICSID was supposed to adopt the decision on its competence by the end of 2018, but its was postponed by the end of first quarter of 2019. However, the Center is silent since then and has not informed RiTE Ugljevik regarding any progress in the arbitration case.

In 2014, Slovenian company Elektrogospodarstvo has submitted a lawsuit against BiH at International Center for Settlement of Disputes (ICSID) in Washington, claiming the amount of 750 million euros. If BiH loses this dispute, with all interest it will be obliged to pay almost 1.5 billion euros. The arbitration proceedings started in late 2015. During the construction of TPP Ugljevik in 1981, Bosnia and Herzegovina invested two-thirds of the necessary funds, while Slovenia invested the remaining funds. When TPP became operational in 1985, Slovenians required regular deliveries of produced electricity in accordance with the funds they invested in the construction. The civil war in former Yugoslavia interrupted this deal and deliveries have been stopped since then. The lawsuit was filed by the company Elektrogospodarstvo which has no employees according to Slovenian business directory, but it has an open support of the Government of Slovenia for the case against Bosnia and Herzegovina.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

Coal regains ground in SEE merit order as gas generation declines

Southeast Europe’s thermal generation mix shifted noticeably toward coal and lignite in Week 34, providing another indication that elevated gas prices are reshaping the short-term economics of conventional power generation across the region. Total thermal electricity generation across the monitored...
Supported byVirtu Energy