Bosnia and Herzegovina, EPBiH is focusing on the project for the construction of unit 8 at TPP Kakanj

Besides the project for the construction of unit 7 at coal-fired thermal power plant Tuzla, Bosnian power utility EPBiH is also focusing on the project for the construction of unit 8 at TPP Kakanj.

Evidently, the difficulties in the implementation of TPP Tuzla project did not defer EPBiH from investments in new coal-fired generation capacities. Namely, the Federal Ministry of Environment and Tourism received application for the issuance of the environmental permit for 300 MW cogeneration (heat and power) unit at TPP Kakanj. The previous permit issued in 2017 was annulled by the Cantonal Court in Sarajevo.

Unit 8 at TPP Kakanj is replacement unit for already decommissioned blocks 1, 2, 3 and 4, as well as unit 5, which is supposed to be shutdown following the commissioning on unit 8.

TPP Kakanj has seven units with total installed capacity of 578 MW, of which only 450 MW in three units is operational, while the first four units were closed in late 1990s.

The new units will be supplied with coal from Kakanj, Breza and Zenica mines. The expected annual generation of the unit is 1,755 GWh, while the investment should amount to 500 million euros, with additional 100 million euros investment in coalmines.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy