Bosnia and Herzegovina: Desulfurization facility at TPP Ugljevik entered trial operation

The newly installed flue gas desulfurization facility at coal-fired thermal power plant Ugljevik, a project worth some 80 million euros, has entered trial operation.
The project manager Zlatko Malovic said that the test phase was launched on 5 December and is expected to last three months. He stressed that the completion of this project eliminates all potential threats that have been growing will the tightening of the environmental legislation in respect of the contractual obligations towards the European Energy Community and the domestic legislation.

The installation of a flue gas desulfurization system, which will be the first of its type in the Balkans area, with funding procured from Japan International Cooperation Agency as a loan. The project is of great importance for the country’s ecology, as well as for the general development and continuation of electricity production in this coal-fired power plant. The construction of the facility started in May 2017.

The agreement on the installation of flue gas desulfurization system between coalmine and thermal power plant (RiTE) Ugljevik and Japanese Mitsubishi was signed in July 2016. In late 2017, Japanese Yokogawa Electric Corporation announced that it will deliver a control system for a flu gas desulfurization system for TPP Ugljevik. The project will be managed by Yokogawa’s Austrian subsidiary and the Serbian Office of Yokogawa Europe. The facility will extend the plant’s operational life until 2035 and will help Bosnia and Herzegovina meet the environmental requirements for joining the EU.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy