Bosnia and Herzegovina, Construction of HPPs on the Bistrica river has not yet started

The delegation from the Republic of Srpska (RS) led by Prime Minister Radovan Viskovic returned from Beijing in December 2019 with a contract to build three hydropower plants on the Bistrica river near Foca.

Today, 19 months later, this project still exists only on paper, while the company that has a concession for these facilities is accumulating losses because it has nothing to do. The main reason why construction did not start is that ERS cannot find the funding for this project.

With the contract signed with the Chinese company AVIC, the value of the project is 102.8 million euros. At the end of March this year, ERS made a decision to seek for a bank through a tender, which will provide them with a loan worth 68.7 million euros, which is 63 % of the value of the project, however, there were no interested banks. Specifically, one Chinese bank was interested but failed to provide documentation in accordance with the Public Procurement Law, so it did not even submit a bid, which is why the procedure was terminated and annulled.

While ERS is seeking for money, the company “Hidroelektrane Bistrica” is accumulating losses. Thus, in the past, they made a loss of some 190,000 euros, which should not be surprising if we take into account that it has five employees and no revenues. Its business plan also shows that the plan is to make a loss of over 300,000 euros in this and next year.

ERS bought the project company for 10.6 million euros in 2019.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

ERS unit seeks €11m capital boost for HE Bistrica hydropower project

Proposed recapitalisation and shareholder vote Hidroelektrane na Drini, part of Bosnia and Herzegovina’s Serb power utility ERS, is preparing another recapitalisation of the project company HE Bistrica. The latest proposal would convert around €11 million of short-term loans into permanent...

Hrgud 60-MW wind farm tender halted by complaint in Bosnia and Herzegovina

A formal complaint has stopped the latest procurement for the 60-MW Hrgud wind farm in Bosnia and Herzegovina, extending delays for one of Republika Srpska’s longest-running renewable-energy projects. The procurement cannot proceed on its original timetable until the objection...

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...
Supported byVirtu Energy