Bosnia and Herzegovina, CHPP Zenica commissioned

Bosnian steel mill ArcelorMittal Zenica, in cooperation with the Municipal Government of Zenica and two Finish companies, officially commissioned a new combined heat and power (CHP) plant in the city.

ArcelorMittal Zenica, the city of Zenica, KPA Unicon and FinnFund cooperated on the project for the construction of 53 million euros CHP plant, which consists of three boilers. The investors financed the project with a 41 million euros loan from the European Bank for Reconstruction and Development (EBRD), guaranteed by ArcelorMittal. The remaining 12 million euros was provided by the investors themselves.

The new CHPP has a power output of 14.45 MW and a heat capacity of 112.5 MW. The construction was launched in March 2020. The new plant will not use coal, leading to the complete elimination of SO2 emissions and a more stable supply of heat to consumers, as well as a reduction of CO2 emissions by some 200,000 tons per year.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Republika Srpska accelerates generation and gas projects after drought curbs output

Energy and Mining Minister Petar Djokic said electricity production in Republika Srpska can normally run about 35% above domestic demand. He added that the buffer narrowed during summer due to dry weather cutting hydropower output. The Ugljevik thermal power...

Bosnia-Croatia southern gas interconnection delayed over financing and land issues

Agreement talks with AAFS Infrastructure & Energy Plans for the Southern Gas Interconnection between Bosnia and Herzegovina and Croatia remain delayed as developers work through financing, state-property and interstate-agreement issues. A planned agreement with US company AAFS Infrastructure & Energy,...

EU CBAM revisions could cut Bosnia electricity exporters’ costs by up to €13 million

Proposed changes to the European Union’s Carbon Border Adjustment Mechanism could reduce the cost faced by Bosnia and Herzegovina’s electricity exporters by as much as €13 million annually. Bosnia says the revisions could save exporters €13 million a year,...
Supported byVirtu Energy