Šoštanj Unit 6 restart planned for October after intermediate-pressure turbine damage

Slovenia’s Šoštanj thermal power plant expects to bring Unit 6 back to service before the winter heating season following inspections that uncovered damage in the turbine’s intermediate-pressure section. The restart is targeted for October, according to the plant’s schedule for returning the unit ahead of seasonal demand.

Damage found during planned summer overhaul

Elevated vibration was detected shortly before the unit entered its planned summer overhaul. Engineers working with specialists from GE Steam Power identified damage in the turbine’s labyrinth section, leading to a wider technical inspection.

The inspection results pointed to an issue affecting the turbine’s intermediate-pressure section. Further checks were expanded beyond the initial findings as part of the technical review.

Refurbishment in Berlin and further high-pressure checks

The affected component cannot be repaired in Slovenia and was transported to GE’s facility in Berlin for refurbishment. The turbine’s high-pressure section is also undergoing a full inspection as a precaution against additional defects.

Commissioning tests are scheduled to begin in mid-October 2026, provided the repair is completed and inspections deliver satisfactory results. The timing is intended to allow Unit 6 to return before electricity and district-heating demand increases during winter.

Regional generation constraints and settlement arrangements

The outage has implications beyond Šoštanj itself. Slovenia is already exposed to lower nuclear production at Krško and hydrological constraints linked to drought and high river temperatures.

A delayed return of Šoštanj would increase reliance on imports during a period when neighbouring systems may face similar generation restrictions. The repair work is being carried out under a settlement agreement previously concluded between the plant and GE.

The settlement includes a long-term service contract worth approximately €110mn, covering planned maintenance, spare parts, manufacturer support and digital upgrades through 2029–2030. The final cost of the current intervention has not been determined, with allocation depending on detailed terms covering warranties, defect responsibility and classification of the damaged component.

Mid-October commissioning window leaves limited contingency

The October target leaves limited schedule contingency for commissioning preparations. Any further defect discovered in Berlin or during reassembly could delay commissioning into the heating season.

The heating season timing is described as materially higher value for the unit, based on system conditions expected during winter demand periods.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia extends application deadline for €68.97m electricity distribution investment

Slovenia has extended the application deadline for its €68.97 million electricity distribution investment programme to 30 November 2026, giving applicants additional time to complete technical documentation. The previous deadline was 31 October. The funding allocation remains unchanged. Funding split and...

Slovenia restarts Sostanj unit 5 to meet district heating demand

Slovenia’s Sostanj thermal power plant has temporarily restarted unit 5 as colder weather increases district heating demand. Unit 6 remains under maintenance while unit 5 is brought back into service. Heat demand has reached approximately 400 MWh a day. Unit...

Slovenia shows EV fleets can become flexible power-market assets

Slovenia has demonstrated that electric-vehicle charging can be managed as a flexible electricity portfolio, rather than treated simply as an additional source of power demand. The approach could create new business opportunities for fleet operators, aggregators, electricity suppliers and...
Supported byVirtu Energy