Šoštanj Unit 6 restart planned for October after intermediate-pressure turbine damage

Slovenia’s Šoštanj thermal power plant expects to bring Unit 6 back to service before the winter heating season following inspections that uncovered damage in the turbine’s intermediate-pressure section. The restart is targeted for October, according to the plant’s schedule for returning the unit ahead of seasonal demand.

Damage found during planned summer overhaul

Elevated vibration was detected shortly before the unit entered its planned summer overhaul. Engineers working with specialists from GE Steam Power identified damage in the turbine’s labyrinth section, leading to a wider technical inspection.

The inspection results pointed to an issue affecting the turbine’s intermediate-pressure section. Further checks were expanded beyond the initial findings as part of the technical review.

Refurbishment in Berlin and further high-pressure checks

The affected component cannot be repaired in Slovenia and was transported to GE’s facility in Berlin for refurbishment. The turbine’s high-pressure section is also undergoing a full inspection as a precaution against additional defects.

Commissioning tests are scheduled to begin in mid-October 2026, provided the repair is completed and inspections deliver satisfactory results. The timing is intended to allow Unit 6 to return before electricity and district-heating demand increases during winter.

Regional generation constraints and settlement arrangements

The outage has implications beyond Šoštanj itself. Slovenia is already exposed to lower nuclear production at Krško and hydrological constraints linked to drought and high river temperatures.

A delayed return of Šoštanj would increase reliance on imports during a period when neighbouring systems may face similar generation restrictions. The repair work is being carried out under a settlement agreement previously concluded between the plant and GE.

The settlement includes a long-term service contract worth approximately €110mn, covering planned maintenance, spare parts, manufacturer support and digital upgrades through 2029–2030. The final cost of the current intervention has not been determined, with allocation depending on detailed terms covering warranties, defect responsibility and classification of the damaged component.

Mid-October commissioning window leaves limited contingency

The October target leaves limited schedule contingency for commissioning preparations. Any further defect discovered in Berlin or during reassembly could delay commissioning into the heating season.

The heating season timing is described as materially higher value for the unit, based on system conditions expected during winter demand periods.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Slovenia opens electricity market to Nord Pool and CROPEX, intensifying exchange competition

Slovenia has opened its wholesale electricity market to competing exchange operators, giving Nord Pool and Croatia’s CROPEX the opportunity to challenge incumbent BSP SouthPool. The move could reshape trading services, market-access costs and operational risk management across Southeast Europe. The...

CROPEX expands into Slovenia’s day-ahead electricity market

Croatian electricity exchange CROPEX has expanded its operations into Slovenia’s day-ahead electricity market, marking a significant step in its regional growth as competition intensifies across Europe’s increasingly integrated power market. CROPEX began operations in Slovenia on October 21 under the...

Slovenian Court Upholds Time-Based Network Tariffs

Slovenia’s Constitutional Court has upheld the revised power grid charging system, rejecting objections to a methodology that links charges more closely to when consumers use electricity and how much network capacity they need. The unanimous ruling keeps in place...
Supported byVirtu Energy