Wind farm Krivaca in eastern Serbia will cover the area of 242 hectares within three municipalities: Golubac, Kucevo and Veliko Gradiste, according to the updated Environmental Impact Assessment (EIA) study for the project.

However, the initial project was changed and instead of 38 wind turbines, the future wind farm will consist of 22. The reason for the reduction of the number of wind turbines is to not exceed the total allowed installed capacity of wind plant of 103.32 MW.

The updated study states that the wind turbines will have greater installed capacity, higher poles and the blades will be larger in diameter compared to the original wind turbines design. The wind turbines will have maximum power output up to 5,8 MW, equipped with a three-blade rotor up to 255 meters maximum in diameter and the total maximum height of the turbines will be up to 205 meters.

In 2016, local company Ivicom Energy, a subsidiary of Austrian Ivicom Energy GmbH, announced that it will invest in the construction of Krivaca wind farm near Golubac in eastern Serbia. According to initial plans, the wind farm was to be put in operation by the end of 2017.

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

500 MW combined-cycle gas plant joint venture advances in Niš

Serbia’s EPS and Srbijagas have agreed with Azerbaijan’s SOCAR to set up a joint venture for a planned 500 MW combined-cycle gas power plant in Niš. The arrangement is intended to advance preparations ahead of a final investment decision....

Gazprom gas extension talks in Serbia as NIS sanctions deadline nears

Serbia expects to extend its gas supply arrangement with Gazprom beyond September 30 while Russian deliveries continue. President Aleksandar Vučić said after a call with Russian President Vladimir Putin that an annex should be signed shortly. The extension’s duration,...

Serbia targets early-2027 start for Romanian gas interconnector construction

Serbia expects construction of its gas interconnector with Romania to begin in early 2027, creating an import route intended to diversify supply and strengthen network resilience. Procurement for the Serbian section is expected to start shortly. Most technical and...
Supported byVirtu Energy