Serbia, Unit B1 of coal-fired TPP Nikola Tesla B (TENT B) entered trial operation

Unit B1 of coal-fired thermal power plant Nikola Tesla B (TENT B) entered trial operation in the early hours of 26 November, following its lengthy overhaul and modernization.

The statement from power utility EPS said that the unit’s installed capacity has been increased by 20 MW to 670 MW, along with an increase of its operational life and efficiency. This is all due to a 90 million euros worth modernization, most of which (70 million euros) was used for the overhaul of the boiler facility.

In addition to the increased capacity, life cycle and efficiency, this revitalization project has also upgraded the conditions of environmental protection. The installation of the system for the reduction of nitrogen oxides will reduce the emission of these compounds to below 200 milligrams per cubic meter.

The installation of desulfurization facilities at TENT A is currently ongoing, while the project for the installation of such facilities at units of TENT B has just started.

Currently, Serbia produces almost 70 % of its electricity from coal and, unlike many European countries, does not have a clear coal phase-out deadline.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

500 MW combined-cycle gas plant joint venture advances in Niš

Serbia’s EPS and Srbijagas have agreed with Azerbaijan’s SOCAR to set up a joint venture for a planned 500 MW combined-cycle gas power plant in Niš. The arrangement is intended to advance preparations ahead of a final investment decision....

Gazprom gas extension talks in Serbia as NIS sanctions deadline nears

Serbia expects to extend its gas supply arrangement with Gazprom beyond September 30 while Russian deliveries continue. President Aleksandar Vučić said after a call with Russian President Vladimir Putin that an annex should be signed shortly. The extension’s duration,...

Serbia targets early-2027 start for Romanian gas interconnector construction

Serbia expects construction of its gas interconnector with Romania to begin in early 2027, creating an import route intended to diversify supply and strengthen network resilience. Procurement for the Serbian section is expected to start shortly. Most technical and...
Supported byVirtu Energy