Supported byClarion Energy
HomeHydroSerbia: Revitalization of...

Serbia: Revitalization of HPP Zvornik

Assembly of the last unit A4

Runner installation marked the finish of one of the most significant phases in Unit A4 revitalization

 

At the Zvornik hydroelectric power plant, as part of the revitalization of the A4 generator, on 9 October, the rotor was transported from the assembly hall and installed into the generator stator, i.e. generator shaft. This completes one of the most important phases in the revitalization of the last unit, and in order to achieve it, a number of assembly works had to be carried out, such as installation of the main components of the turbine, such as the runner, turbine cover, wicket gates, main turbine control components (tanks, pumps, pipelines, servomotors, control ring), installation of the turbine bearing, guide bearing and connection of the generator and turbine shaft. Auxiliary components of the turbine were also mounted: sensors, treads, transducers, equipment supports, etc.

Generator rotor has been completed in the assembly hall of the power plant, from where it was transported and installed, while the installation of the generator stator was done in the generator barrel – at the place of installation.

Installation of almost all primary and secondary electrical equipment, such as 110 kV switchgear, unit transformer, generator buses, generator voltage equipment, control equipment – cabinets, protection and motors and other auxiliary electrical equipment, has been completed.

The cooling water and compressed air systems are largely installed and will be completed in parallel with turbine, turbine control and generator installation.

– In the coming period, the following activities will be completed: installation of the upper cross and the upper generator bearing, installation of the upper generator covers, generator sliding rings and their connection with the rotor poles, installation of the turbine oil head, continuation of equipment cabling, connection of the 110 kV switchgear to the first transmission line serving to connect to unit to the grid – Tomica Jovanovic, head of production department at HPP Zvornik, pointed out.

In addition to mounting, equipment must also be tested and adjusted (fluid leak checking, centering, electrical testing).

Completion of assembly work is planned for November 30, when the unit tests will begin after the installation has been completed. Completion of tests, including a 30-day test run of the unit, is planned for 5 February 2020, when the unit enters commercial operation, i.e. one year warranty period.

Revitalized units A1, A2 and A3 have undergone or are undergoing repairs and eliminating deficiencies observed throughout their operation.

In addition to the revitalization of the A4 generators and the repairs of the A1, A2 and A3 units, activities are underway to obtain permanent grid connection solution of the revitalized HPP Zvornik units, as well as to receive an operating permit.

 

The revitalization of the A4 generator at Zvornik HPP officially began on 11 February 2019. The revitalization project is headed by Voith Hydro, while the subcontractors are mainly domestic companies: Gosa Montaza, Elnos, Mihajlo Pupin Institute and Elektroremont.

Source: EPS Energija

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia, FBiH, and RS Strengthen Hydropower and Gas Connectivity Initiatives

Energy officials from Serbia, the Federation of Bosnia and Herzegovina (FBiH), and the Republic of Srpska (RS) have committed to enhancing collaboration on hydropower development along the Drina River, while also focusing on improving regional gas connectivity. This cooperative...

Renewable Energy’s Shift: From Permitting to Performance Standards

The renewable energy sector in Europe is undergoing a significant transformation, with the focus shifting from project permitting to performance monitoring. This change is particularly relevant for wind farms, solar parks, and hybrid storage facilities, where the criteria for...

Environmental Engineering’s Role in Serbia’s Energy and Mining Sectors

As Serbia embarks on a significant investment cycle across energy, mining, and infrastructure, the importance of environmental engineering has escalated. This shift is not merely about engineering capabilities; rather, it reflects a growing necessity to address environmental constraints that...
Supported byVirtu Energy