Serbia, Overhaul of unit B1 at the plant will be completed by 25 November

During his visit to thermal power plant Nikola Tesla (TENT) B, Serbian President Aleksandar Vucic said that the overhaul of unit B1 at the plant will be completed by 25 November.

The capital overhaul of unit B1, the first one since its commissioning over 40 years ago, started in May this year. The cost of the overhaul is around 90 million euros.

President Vucic said that, due to the downtime of 650 MW unit, Serbia had to import electricity, adding that a part of missing electricity was compensated by importing natural gas.

Currently, Serbia produces 68 % of its electricity from coal, which, according to President Vucic, has to be lowered in the coming period, mostly by building new electricity generation capacities from renewable sources.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia power prices fall as regional market gaps widen

Serbian day-ahead electricity prices fell for delivery on 2 October, moving against increases recorded in most neighbouring markets. The decline widened Serbia’s price discount to Hungary, although sharp evening price peaks showed that lower daily averages did not eliminate...

Serbia: SEEPEX hits record September trading volume as electricity prices increase

Serbia’s SEEPEX day-ahead electricity market recorded its highest-ever monthly trading volume in September, while average electricity prices increased compared with August. Trading turnover reached 579,406.3 MWh, representing a 5.9% increase month on month and a 26.6% rise year on year....

MOL-NIS majority stake talks in Serbia unresolved as October deadline nears

A potential MOL acquisition of a majority stake in Serbia’s NIS remains unresolved as an October deadline approaches, even after a new US authorisation that allows negotiations to continue until 30 October. The US authorisation extends the timeframe for...
Supported byVirtu Energy