Joint venture of Austrian Ivicom and Slovenian H- Planet is planning to build a 150 MW wind farm near Kucevo in eastern Serbia.

According to the detailed regulation plan, the future wind farm will have 30 wind turbines stretching over 1,750 hectares of land in northern part of Kucevo municipality. The turbines will have a maximum diameter of 160 meters and a maximum height (including the wind turbine blade) of 210 meters.

The plan also envisages the construction of the 110 kV transmission line that will connect the facility with the nearby 440 kV line.

The project company VE Rakova Bara, which was established earlier this year, is majority owned by Ivicom (60 %), while H-Planet holds the remaining 40 % stake.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Banatski Dvor expansion delays deepen Serbia’s reliance on Hungarian storage

Serbia’s Banatski Dvor underground gas storage expansion is experiencing further slippage, according to project timelines that have moved past the previously targeted end of 2026. The delay increases the need for additional storage capacity outside Serbia. Serbia rents about...

Hungary granted temporary EU delay on Serbia gas capacity bundling rules

Hungary has received temporary approval from the European Commission to postpone full implementation of EU gas-capacity rules at its border with Serbia until the 2027/2028 gas year. The derogation relates to requirements that cross-border pipeline capacity be offered as...

Serbia launches $600 million gas network modernisation with World Bank support

Serbia has secured a $600 million World Bank framework for a gas-system overhaul. The programme is planned as a decade-long modernisation of Serbia’s gas network. It covers pipelines, underground storage and institutional reforms. Financing and initial pipeline focus The first phase...
Supported byVirtu Energy