Romania, Romgaz expects to complete gas unit at TPP Iernut by the end of 2022

CEO of Romanian natural gas Romgaz Aristotel Jude said that the company is still analyzing the possibility of concluding a new contract with the consortium consisting of Romelectro and Duro Felguera for the completion of the 430 MW gas- fired unit at the Iernut power plant.

However, Jude said that Romgaz expects to complete the unit by the end of 2022, which is three years later than initially planned.

In July, after five extensions of negotiation period, Romgaz has finally terminated the contract concluded with a consortium. The termination comes two and a half months after Romgaz initially announced the imminent termination of the contract signed in 2016 with the consortium of Duro Felguera (Spain) and Romelectro (Romania).

In the meantime, the Romanian Government obtained from the European Commission the permit to prolong the project until the end of June 2022. This approval was necessary because the Government is extending 64 million euros worth state aid for the project.

In late 2020, Romgaz said that it would not grant an extension of the deadline for the completion of the construction of a gas-fired unit at the existing TPP Iernut, which was proposed by project’s contractors – Spanish Duro Felguera and local Romelectro. The agreed deadline for the completion of the project expired on 26 December. The statement from Romgaz said that it will identify the necessary solutions to complete and commission the combined cycle unit at Iernut and will inform of its decision at a later date.

In November 2016, Romgaz has concluded an agreement worth 268 million euros (without VAT) with a consortium of Spanish company Duro Felguera and Romanian Romelectro for a turnkey project for the construction of new 430 MW gas- fired power plant within its Iernut thermal power plant. The deadline for the completion of the new combined cycle power plant is 36 months from the effective date of the contract, which shall be within 5 working days from the date the NIP financing is approved. Romgaz took over Iernut thermal power plant in 2013 from Bucharest-based thermal energy producer ELCEN in exchange for deleting a 145 million euros debt.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania expands flexibility market as industrial demand and telecom batteries enter power system

Romania is beginning to turn electricity demand and previously underused backup infrastructure into tradable flexibility, creating new opportunities for aggregators and virtual power plants across Southeast Europe. Two developments illustrate the shift. Transmission system operator Transelectrica activated Romania’s first balancing...

Romania’s power imports surge as renewable generation declines

Romania’s net electricity imports surged 82.08% to 135.72 GWh in the week ending 20 September, as weaker renewable and hydropower generation increased the country’s reliance on electricity from neighbouring markets. Wind and solar generation in Romania fell by 25.9%, while...

Cernavoda output loss expected to continue into October amid low Danube levels

Romania is expected to remain without output from the Cernavoda nuclear plant into October as low Danube levels continue to restrict cooling conditions. The prolonged outage is occurring during a tight regional power market, with increased reliance on cross-border...
Supported byVirtu Energy