Serbian state-owned power utility EPS has launched a tender for the preparation of project- technical documentation for the construction of a 350 MW unit at coal-fired thermal power plant Kostolac.

According to tender documentation, the project for the construction of a new unit will be realized in 14 phases. It includes the design of the unit itself as well as other parts which pertain to the disposal and storage of ash, traffic routes and a cooling system using the water from the Danube. The unit will be highly-efficient, and the network output is expected to be 308 MW.

The tender is open until 22 November.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia and SOCAR near joint venture for up to 500 MW gas-fired CHP

Serbia is close to setting up a joint venture with Azerbaijan’s SOCAR to develop a gas-fired combined heat and power plant. The planned facility would have capacity of up to 500 MW. The project is being advanced through negotiations...

Serbia’s power system recovery meets continued lignite dependence and rising project costs

Generation mix after earlier operational issues A 2025 energy-sector assessment says Serbia’s electricity system has recovered from severe operational problems earlier in the decade, but the sector remains exposed to further shocks. Continued reliance on lignite, higher infrastructure costs and...

Serbia maintains power price advantage as volatility challenges export potential

Serbia maintained one of the more competitive wholesale electricity positions in Southeast Europe during the second half of August, supported by stronger hydro, renewable and thermal generation. However, the sharp increase in prices at the beginning of September demonstrated...
Supported byVirtu Energy