Serbia: Construction begins on new 400 kV transmission line connecting Obrenovac and Bajina Bašta

Construction has officially started on a new 400 kV dual-circuit transmission line linking Obrenovac to Bajina Bašta, marking a major advancement in Serbia’s energy infrastructure. This project, initiated near the Obrenovac substation, is part of the wider Trans-Balkan Corridor and aims to improve regional electricity transmission capacity and system stability.

Stretching over 109 kilometers, this high-voltage line represents the third phase of the Trans-Balkan Corridor—one of the region’s most strategically significant energy initiatives. The new line will replace the existing 220 kV infrastructure in western Serbia, enhancing both capacity and reliability of the national grid.

A key benefit of the project is its support for the planned Bistrica pump-storage hydropower plant, which is expected to play a crucial role in balancing Serbia’s electricity system amid growing renewable energy integration. The total investment for this segment is estimated at approximately 100 million euros. Funding sources include a 64.5 million euro loan from the German development bank KfW, 21 million euros in grants from the Western Balkans Investment Framework (WBIF), and additional contributions from Serbia’s transmission system operator EMS.

Following an international tender, the construction contract was awarded to local company Kodar Energomontaža. Completion is scheduled for 2027.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Serbia and SOCAR near joint venture for up to 500 MW gas-fired CHP

Serbia is close to setting up a joint venture with Azerbaijan’s SOCAR to develop a gas-fired combined heat and power plant. The planned facility would have capacity of up to 500 MW. The project is being advanced through negotiations...

Serbia’s power system recovery meets continued lignite dependence and rising project costs

Generation mix after earlier operational issues A 2025 energy-sector assessment says Serbia’s electricity system has recovered from severe operational problems earlier in the decade, but the sector remains exposed to further shocks. Continued reliance on lignite, higher infrastructure costs and...

Serbia maintains power price advantage as volatility challenges export potential