Supported byClarion Energy
HomeHydroSerbia Advances Bistrica...

Serbia Advances Bistrica Pump-Storage Hydropower Project

In a significant move for its energy sector, Serbia has approved land expropriation for the Bistrica pump-storage hydropower plant, marking a crucial step in the project’s administrative process. This designation of public interest facilitates the acquisition of necessary land for construction and associated infrastructure, thereby advancing the project into its implementation phase.

The expropriation will encompass various cadastral zones within the municipalities of Nova Varoš and Priboj, including key areas such as Radoinja, Rutoši, Seništa, Čelice, Kratovo, and Pribojske Čelice. The acquisition process is set to adhere to existing spatial planning documents related to both the Bistrica project and the adjacent Poteć hydropower system, ensuring compliance with relevant spatial and regulatory frameworks.

Elektroprivreda Srbije (EPS), Serbia’s state-owned power utility, has been designated as the beneficiary of this expropriation. Following the completion of legal procedures, EPS will gain control over the land and facilities necessary for advancing construction efforts. This responsibility positions EPS at the forefront of both project execution and future asset management, highlighting its pivotal role in Serbia’s energy landscape.

The Bistrica hydropower project aligns with Serbia’s broader strategy to enhance its electricity system’s resilience by increasing flexibility through pump-storage capabilities. Authorities anticipate that this facility will significantly contribute to supply balancing and overall system performance enhancement. It is expected to bolster grid stability while facilitating the integration of variable renewable energy sources. Preparatory activities are slated to commence within this year, signaling a shift from planning stages to on-the-ground implementation.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPS opens renewable M&A channel for Serbian wind, solar and hybrid projects

Serbia’s state-owned power utility EPS has opened a formal channel to acquire or partner with privately developed renewable energy projects of at least 50 MW, creating a potential exit opportunity for developers as grid access, financing and market conditions...

Serbia and SOCAR near joint venture for up to 500 MW gas-fired CHP

Serbia is close to setting up a joint venture with Azerbaijan’s SOCAR to develop a gas-fired combined heat and power plant. The planned facility would have capacity of up to 500 MW. The project is being advanced through negotiations...

Serbia’s power system recovery meets continued lignite dependence and rising project costs

Generation mix after earlier operational issues A 2025 energy-sector assessment says Serbia’s electricity system has recovered from severe operational problems earlier in the decade, but the sector remains exposed to further shocks. Continued reliance on lignite, higher infrastructure costs and...
Supported byVirtu Energy