Romania, Transelectrica to publish available connection capacities for RES projects

According to new regulation drafted by the National Regulatory Authority for Energy (ANRE). electricity transmission system operator Transelectrica will have to evaluate and publish the volume and location of transmission capacities available for renewable energy projects.

The regulation is needed to determine how much green energy can be absorbed by the electricity transmission network, while respecting the quality indicators of the electricity transmission and distribution services and maintaining constant security. This particurarly pertains to 110 kV networks.

Starting with 1 December , Transelectrica will publish the data every month, then starting with 1 April 2022, twice a month, from 1 July the data will be published on the weekly basis and, finally, as of 1 October, daily.

According to the National Recovery and Resilience Plan (PNRR), Romania plans to add 6.9 GW of new renewable energy capacity by 2030, of which more than 3.7 GW will be solar capacity.

Earlier this year, Transelectrica said that no new electricity generation capacities could be licensed for connection to the network in southeastern Romania (Dobrogea and surrounding regions) until the ongoing projects for increased the network’s capacity are completed.

The statement was not specific in regard to the type of generation capacities, but it is particularly relevant for the renewable energy (solar and especially wind) projects that were already launched or are planned in the region, as part of a new wave of such investments after the slowdown prompted by the change in regulations around 2013. Another reason is slow implementation of Transelectrica’s projects in this part of the country, i.e. some investments launched 18 years ago have not been yet completed.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Transelectrica launches €90.4m digital upgrade for Alba Iulia 220/110/20 kV substation

Romanian transmission operator Transelectrica has launched a €90.4 million upgrade of its Alba Iulia 220/110/20 kV substation, excluding VAT. The project is intended as a pilot for broader digitalisation of the national grid. The scope links substation equipment with...

Rezolv financing up to €561 million for 1.3 GW Dama Solar in Romania

Rezolv Energy has secured financing of up to €561 million for its 1.3 GW Dama Solar development in western Romania, enabling the project to move into construction ahead of planned commercial operation in the second half of 2028. The...

Romania’s Romgaz rejects 20-year US LNG contract amid projected losses

Romanian gas producer Romgaz has rejected a proposed 20-year US LNG contract. The company said its assessment pointed to potential annual losses ranging from €50 million to €310 million, depending on US and European gas prices. The offer was put...