Supported byClarion Energy
HomeElectricityRomania: Suspension of...

Romania: Suspension of termination notice for TPP Iernut extended

The negotiations over thermal power plant Iernut are extended until 20 May.

Romanian natural gas producer Romgaz has extended, by another two weeks, the suspension of the notice of termination of the contract concluded with a consortium of Spanish Duro Felguera and local Romelectro for the construction of a gas unit at TPP Iernut, because changes were made at the level of Duro Felguera’s management and it requested to resume negotiations in order to identify solutions regarding the project’s completion as soon as possible.

In early April, Romgaz said that it has decided to temporary suspend the termination of contract for the construction of a gas-fired unit at thermal power plant Iernut with the aforementioned consortium. The statement from the company said that it has suspended for 14 days the notice on the contract’s termination at the consortium’s request. Within that timeframe, , the consortium will submit a proposal about finalizing the works and putting the plant into operation as soon as possible. In late 2020, Romgaz said that it would not grant an extension of the deadline for the completion of the construction of a gas-fired unit at the existing TPP Iernut, which was proposed by project’s contractors – Spanish Duro Felguera and local Romelectro. The agreed deadline for the completion of the project expired on 26 December. The statement from Romgaz said that it will identify the necessary solutions to complete and commission the combined cycle unit at Iernut and will inform of its decision at a later date. In November 2016, Romgaz has concluded an agreement worth 268 million euros (without VAT) with a consortium of Spanish company Duro Felguera and Romanian Romelectro for a turnkey project for the construction of new 430 MW gas-fired power plant within its Iernut thermal power plant. The deadline for the completion of the new combined cycle power plant is 36 months from the effective date of the contract, which shall be within 5 working days from the date the NIP financing is approved. Romgaz took over Iernut thermal power plant in 2013 from Bucharest-based thermal energy producer ELCEN in exchange for deleting a 145 million euros debt. Initially, the plant was supposed to be commissioned in early 2020, but delays have arisen, both as a result of disagreements between partners regarding the provisions of GEO 114/2018 and regarding the increase in construction costs.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Serbia and SOCAR near joint venture for up to 500 MW gas-fired CHP

Serbia is close to setting up a joint venture with Azerbaijan’s SOCAR to develop a gas-fired combined heat and power plant. The planned facility would have capacity of up to 500 MW. The project is being advanced through negotiations...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...
Supported byVirtu Energy