Romania: Modernization of Iron Gates I HPP

Electricity producer Hidroelectrica said that it has signed the procurement contract for the modernization of the electrical installations related to the hydromechanical equipment at the Iron Gates I hydropower plant.

The works, initially estimated by Hidroelectrica at 12.5 million euros without VAT, was awarded to a consortium consisting of DSD Noell GmbH and UTI Facility Management, with the offer 11.5 million euros. Romelectro submitted the other offer at the tender launched last October. The statement from the company said that the contract continues the series of major investments in the power plant, after the modernization of the SCADA systems in the control rooms for both HPP Igron Gates I and II and the modernization of the monitoring and diagnosis system at HPP Iron Gates I.

Iron Gates I or Djerdap I is one of the largest hydropower plants in Europe and the largest dam on Danube. The Romanian side of the HPP has six 194.3 MW turbines, while Serbian side has four 171 MW and two 201 MW turbines. Annual electricity generation is about 5.4 TWh on the Romanian and 5.65 TWh on the Serbian side.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

TDI financing for 58 MW Iratoșu solar plant in western Romania

TDI Renewables has secured €25.5 million in financing from Raiffeisen Bank International for its 58 MW Iratoșu solar power plant in western Romania. The project is located in Arad county and is part of a broader development programme that...

Nuclearelectrica revises 2026 outlook as Cernavoda outages drive replacement power costs

Romanian nuclear producer Nuclearelectrica has reduced its forecast for 2026 net profit by 42.9% to €221 million. The company attributed the change to prolonged outages at Cernavoda, which have lowered electricity sales and required purchases of replacement power. Revised...

Romania extends 25% diesel excise reduction until Oct. 31

Romania will keep a 25% reduction in diesel excise duty until Oct. 31, extending temporary relief for transport operators and other businesses. The decision follows a period in which international fuel-market prices have risen faster than domestic pump prices....
Supported byVirtu Energy