Hidroelectrica has completed the filling procedure at normal retention level of 1072.5 meters of Gura Apelor lake, the accumulation belonging to Raul Mare Retezat project.

The filling of the lake, which covers about 360 hectares and accumulates about 220 million cubic meters of water, was possible only this year, amid favorable hydrology.

Gura Apelor dam is the second largest clay core rock dam in Europe, the construction encompassing 7 million cubic meters of stone from quarries in the area, as well as one million cubic meters of land. The building, 160 meters high, is placed on a wide base of 560 meters and extends 460 meters long at the canopy.

HPP Raul Mare Retezat complex includes the Gura Apelor dam and the Retezat and Clopotiva hydropower plants, with an installed capacity of 349 MW and an average annual electricity generation of 629.5 GWh.

The filling of the accumulation is also the precondition for the start of the project for the reconstruction of the HPP complex. Earlier this year, Hidroelectrica has launched a 77 million euros worth tender for the reconstruction of the complex. The reconstruction includes: procurement, assembly and commissioning of hydraulic turbine; procurement, assembly and commissioning of generator; modernization, installation and commissioning of hydromechanical equipment; modernization and commissioning of transformer stations; installation and commissioning of automation and SCADA systems.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Transelectrica launches €90.4m digital upgrade for Alba Iulia 220/110/20 kV substation

Romanian transmission operator Transelectrica has launched a €90.4 million upgrade of its Alba Iulia 220/110/20 kV substation, excluding VAT. The project is intended as a pilot for broader digitalisation of the national grid. The scope links substation equipment with...

Rezolv financing up to €561 million for 1.3 GW Dama Solar in Romania

Rezolv Energy has secured financing of up to €561 million for its 1.3 GW Dama Solar development in western Romania, enabling the project to move into construction ahead of planned commercial operation in the second half of 2028. The...

Romania’s Romgaz rejects 20-year US LNG contract amid projected losses

Romanian gas producer Romgaz has rejected a proposed 20-year US LNG contract. The company said its assessment pointed to potential annual losses ranging from €50 million to €310 million, depending on US and European gas prices. The offer was put...
Supported byVirtu Energy