In order to replace classic/non-insulated low voltage conductors in the electricity network with insulated ones, in 8 localities in the Suceava County, Electricity and natural gas distributor Delgaz Grid, a part of German E.ON, made an investment of some 4 million euros.

The works carried out within these investments will contribute to the significant reduction of the time and duration of power supply interruptions in case of breakdowns in the electricity distribution system. In the end, 51 kilometers of overhead transmission lines will be modernized, 2,000 connections will be replaced and a new low voltage network will be built, in a length of 12.3 kilometers.

This year, Delgaz Grid budgeted investments of 126 million euros, a priority for the modernization and expansion of natural gas and electricity distribution networks. The budget allocated to investments is 11 % higher than in the previous year, being also the largest in the last 16 years, since E.ON entered the Romanian energy market.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania delays Cernavodă restart amid Danube drought, extending nuclear outage

Romania is unlikely to restart either reactor at the Cernavodă nuclear plant for at least another 10 days, pushing recovery beyond mid-September. The delay extends the loss of around 1.3-1.4 GW of baseload generation and keeps Romania reliant on...

Rompetrol Rafinare boosts Petromidia storage capacity amid refinery upgrade

Rompetrol Rafinare is expanding storage capacity at its Petromidia refinery as part of a programme aimed at improving the flexibility and reliability of crude oil and fuel logistics. The company’s works include changes to tank capacity and refurbishment across...

Romania emergency Danube measures for cooling-water supply at Cernavoda

Three-stage plan tied to intake basin water level Romania has approved an emergency intervention plan aimed at maintaining cooling-water supplies for the Cernavoda nuclear power plant amid exceptionally low Danube levels. The measures would be triggered if the water level...