Energy supplier and distributor Electrica said its project subsidiary Sunwind Energy has signed a 19.3 million euro engineering, procurement and construction (EPC) contract for the development of a 27 MW solar park in Romania.

The undisclosed developer will build the Satu Mare 2 solar park and a 110 kV substation, operating and maintaining the site for three years after commissioning, Electrica said in a report filed with the Bucharest Stock Exchange.

Electrica expects the project to be completed by late 2024.

The solar project is financed through non-refundable funds disbursed through Romania’s National Recovery and Resilience Plan (NRRP) in October 2023. According to documents published on Romania’s NRRP project portal, the total financing package is worth 110.1 million lei (22.2 million euros).

In March 2023, Electrica completed the full acquisition of the Sunwind Energy project company from businessmen Emanuel Muntmark and Catalin Mrejeru. In January 2024, Sunwind Energy launched a tender for the EPC contract aimed at the construction of the ready-to-build Satu Mare 2 solar project.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania expands flexibility market as industrial demand and telecom batteries enter power system

Romania is beginning to turn electricity demand and previously underused backup infrastructure into tradable flexibility, creating new opportunities for aggregators and virtual power plants across Southeast Europe. Two developments illustrate the shift. Transmission system operator Transelectrica activated Romania’s first balancing...

Romania’s power imports surge as renewable generation declines

Romania’s net electricity imports surged 82.08% to 135.72 GWh in the week ending 20 September, as weaker renewable and hydropower generation increased the country’s reliance on electricity from neighbouring markets. Wind and solar generation in Romania fell by 25.9%, while...

Cernavoda output loss expected to continue into October amid low Danube levels

Romania is expected to remain without output from the Cernavoda nuclear plant into October as low Danube levels continue to restrict cooling conditions. The prolonged outage is occurring during a tight regional power market, with increased reliance on cross-border...