Romania: Cernavoda-Stalpu construction of transmission line project

The first two and a half months of works on the construction of 400 kV Cernavoda-Stalpu double-circuit overhead transmission line a total of 45 poles has been erected, with an average of 1.5 poles built per day, said Romanian electricity transmission system operator Transelectrica.

The works at the 400 kV Cernavoda-Stalpu line started in March 2020, with the completion deadline on March 2022. The investment of 59 million euros aims to consolidate the cross section between the west coast of the Black Sea (eastern Romania) and the rest of the transmission system. At the same time, it will contribute to the strengthening of the Romanian electricity transmission network, to the increase of the interconnection capacity between Romania and Bulgaria and to the integration of the wind energy in the Dobrogea region.

In 2018, Transelectrica received a first tranche of 2.2 million euros of a 27 million euros grant from the European Commission (EC) for the construction of a 400 kV transmission line between Cernavoda and Stalpu. The new 400 kV line will have a length of some 160 kilometers and the project also includes the construction of 400 kV Stalpu substation and the expansion of the existing Cernavoda and Gura Ialomitei substations. The total value of the grant approved by the EC via the Connecting Europe Facility (CEF) amounts to 27 million euros. This amount covers 50 % of the investment, while the rest of the amount will be covered through the company’s own financial sources.

 

 

 

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Transelectrica launches €90.4m digital upgrade for Alba Iulia 220/110/20 kV substation

Romanian transmission operator Transelectrica has launched a €90.4 million upgrade of its Alba Iulia 220/110/20 kV substation, excluding VAT. The project is intended as a pilot for broader digitalisation of the national grid. The scope links substation equipment with...

Rezolv financing up to €561 million for 1.3 GW Dama Solar in Romania

Rezolv Energy has secured financing of up to €561 million for its 1.3 GW Dama Solar development in western Romania, enabling the project to move into construction ahead of planned commercial operation in the second half of 2028. The...

Romania’s Romgaz rejects 20-year US LNG contract amid projected losses

Romanian gas producer Romgaz has rejected a proposed 20-year US LNG contract. The company said its assessment pointed to potential annual losses ranging from €50 million to €310 million, depending on US and European gas prices. The offer was put...
Supported byVirtu Energy