The electricity sector in the Republic of Srpska (RS) has shown resilience in 2025, navigating significant operational hurdles while continuing to attract investments. The region faced severe hydrological challenges and encountered difficulties with thermal power generation due to inconsistent coal quality and supply interruptions. Despite these setbacks, the reliability of electricity supply remained intact, and consumer prices continued to rank among the lowest in Southeast Europe.

A significant development was marked by the completion of the main tunnel at HPP Dabar, a key project within the Upper Horizons hydropower system. Initially proposed over seventy years ago, this project has faced numerous delays attributed to political strife, administrative hurdles, and legal challenges. The recent breakthrough of the 12-kilometer tunnel, executed with local expertise, signifies a major advancement in infrastructure development. The hydropower plant is being constructed on a turnkey basis in collaboration with China’s Gezhouba Group, with initial operations anticipated by late 2027 or early 2028.

Once operational, HPP Dabar is expected to generate more than 500 GWh of electricity annually, which will help mitigate the shortfall experienced during this dry year. Current production forecasts suggest that hydropower facilities along the Trebišnjica River will likely exceed their output expectations, while plants on the Vrbas River are performing as planned. In contrast, the Drina facilities are projected to produce slightly below target levels.

On the thermal side, TPP Gacko has emerged as the most dependable producer despite facing challenges related to coal quality and undergoing a major maintenance overhaul lasting 68 days. The plant managed to surpass its annual generation targets and accounted for nearly one-third of total domestic electricity consumption.

To address any remaining supply deficits, RS has relied on electricity imports, ensuring that both households and industries received uninterrupted power throughout the year. This strategic approach has allowed the RS power system to maintain stability even under some of the most challenging operational conditions witnessed in recent times.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Bosnia and Herzegovina: ERS secures new loans as Ugljevik shutdown intensifies financial strain

Bosnia and Herzegovina’s state-owned power utility ERS has secured another €2 million in short-term financing, bringing the total amount of new borrowing arranged within just a few days to €7 million. The additional funds come as the company faces...

EPBiH coal shortages raise risk of further electricity tariff pressure in 2026-2027

EPBiH, the state-owned power utility in Bosnia and Herzegovina, faces renewed electricity-price pressure as coal supply problems contribute to losses. The company could see pressure for another electricity-price increase by late 2026 or early 2027, according to the conditions...

Republika Srpska to raise electricity prices from 2027 amid Ugljevik coal issues

Businesses in Republika Srpska are expected to see higher electricity prices starting in January 2027, with households facing increases from March. The authorities are also seeking to strengthen the power sector’s finances while addressing coal supply problems that could...