OMV Petrom has commissioned a new aromatics production unit at its Petrobrazi refinery in Romania following a €140 million investment. The installation is designed to replace equipment that has been in operation since 1961. The project aims to expand output of aromatic compounds and high-octane fuel components.

Benzene extraction and higher-octane fuel components

A central function of the unit is the extraction of benzene from gasoline streams. This process supports the production of fuels intended to meet current European fuel standards. Alongside benzene extraction, the facility is set to increase production of toluene.

Toluene produced at the site is described as a petrochemical feedstock used in manufacturing paints, coatings, and adhesives. After commissioning, annual toluene output is expected to rise by around 50,000 tons. The company expects total toluene capacity to reach approximately 100,000 tons per year.

Efficiency, emissions and broader Petrobrazi modernization

OMV Petrom said the new unit will improve energy efficiency and reduce operational emissions compared with the equipment it replaces. Since acquiring the refinery, the company has invested more than €2 billion in modernization projects at Petrobrazi. The aromatics commissioning forms part of ongoing upgrades at the site.

Planned €750 million SAF, HVO and green hydrogen facilities

In parallel with the aromatics project, OMV Petrom is developing another major initiative at Petrobrazi with a total investment of €750 million. The plan includes facilities for sustainable aviation fuel (SAF) and hydrotreated vegetable oil (HVO). It also covers green hydrogen production at the same location.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Romania approaches electricity import limit as Turceni outage tightens power supply

Romania is moving closer to the physical limits of its electricity import capacity as domestic generation weakens and regional power markets tighten. The situation became more critical after another 285 MW coal-fired unit went offline, increasing the country’s exposure...

Romania: New electricity retail opportunities emerge as energy communities gain supplier options

Romania is reshaping the commercial framework for energy communities, potentially creating a new segment of the electricity retail market in which communities can choose between purchasing only their residual electricity needs from an external supplier or placing their entire...

Greenvolt project financing totals €284 million for Romania’s Gurbanesti wind farm

Financing package for 253.1 MW Gurbanesti project Greenvolt has secured €284 million in project financing for its 253.1 MW Gurbanesti wind farm in Romania, as part of the company’s Wind Rose platform. The financing brings total funding arranged for the...
Supported byVirtu Energy