North Macedonia: KfW grants €55 million loan for solar and wind energy projects

The German development bank KfW has approved a €55 million loan to North Macedonia’s state-owned power utility, ESM, to finance the construction of the Bitola 2 solar power plant and the expansion of the Bogdanci wind farm.

According to a statement from the North Macedonian Ministry of Finance, the state-backed loan has a 15-year term, which includes a five-year grace period. The Bitola 2 solar power plant, with a minimum capacity of 50 MW, will be constructed on reclaimed land near the TPP Bitola. It is expected to generate between 80 and 90 GWh of electricity annually, enough to power over 20,000 households. The total investment in this project is estimated at €47.3 million.

The expansion of the Bogdanci wind farm will increase its total capacity from 36.8 MW to 50 MW. This wind farm has been operational since July 2015.

In addition to this loan, earlier this week, ESM also announced a €5 million EU grant from the European Bank for Reconstruction and Development (EBRD) for the construction of two new solar power plants, with a combined capacity of 30 MW.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia’s electricity trading jumps 74% as September prices rise

Electricity traded on North Macedonia’s MEMO day-ahead exchange rose 74% year on year to 179.2 GWh in September, pointing to increased participation and growing use of the organised electricity market. Despite the strong annual increase, trading volumes fell 10.3% from...

Serbia plans North Macedonia gas interconnector construction start, aiming Q1 2028

Pipeline scope and early works near Vranjska Banja Serbia is targeting early 2028 completion for its gas interconnector with North Macedonia, with construction planned to start and reach completion in the first quarter of 2028. Initial works near Vranjska Banja...

North Macedonia targets 2027 construction start for €1.5 billion Čebren-Galište hydro project

North Macedonia is targeting a 2027 construction start for the long-planned Čebren and Galište hydropower projects, reviving a combined investment of up to €1.5 billion after years of unsuccessful concession attempts. Čebren is planned with a capacity of around 333...
Supported byVirtu Energy