North Macedonia, Daily production of ESM 19 GWh

The production of Macedonian state power plants, AD ESM, was close to 19,000 MWh per day until Saturday evening, which was enough to cover the total consumption on the regulated market, i.e. the demand of households and small consumers as well as the largest part of additional supply, in accordance with the government’s decision. This means that only a small part of the required electricity is imported. After the inclusion of the third unit of TPP Bitolj, an additional increase in production is planned, according to the ESM press release.

The transformer for Block 3 REK Bitolj was delivered to the power plant circuit, according to ESM. The installation will follow, and the start of production is expected in the next ten days. This opens up the possibility that all three units of REK Bitolj, as well as other power plants, will operate at maximum capacity in January, it added.

However, the Oslomej thermal power plant was shut down on Saturday evening due to a problem with a fan in the ash removal section, which led to a minor fire, ESM said later.

It is expected that the power plant will be back in operation as soon as possible. The stoppage will not cause a shortage of electricity in the system, and consumption will be covered by other production capacities, ESM says.

Source: novamakedonija.com.mk

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

North Macedonia aims for 38% renewables share by 2030

North Macedonia is targeting 38% renewable energy as a share of gross final energy consumption by 2030. The programme includes rapid solar expansion and additional hydropower generation, with parts of the plan reported to be ahead of the planned...

North Macedonia generation drops 22% in July as renewables rise

North Macedonia’s gross electricity generation declined 22.3% year on year to 460,035 MWh in July, even as hydro and wind output increased. The month’s generation mix included higher contributions from hydropower and wind compared with the same period a...

Envision selected for turbines in Stip wind project first phase, North Macedonia

Alcazar Energy Partners has reached financial close for the Stip wind project in North Macedonia. The first phase totals 131.25 MW and has moved toward construction after securing financing and selecting Envision Energy as turbine supplier. The project is...