Montenegro, Technical losses in the electricity network in the distribution and transmission system amounted to 492.GWh in 2020

Technical losses in the electricity network in the distribution and transmission system amounted to 492.44 GWh in 2020, which cost end consumers in Montenegro 21.3 million euros.

According to data from the Energy Regulatory Agency (REGAGEN), electricity distribution system operator (CEDIS) and electricity transmission system operator (CGES), losses in the transmission network amounted to 9.22 million euros, while those in the distribution system to 12 million euros. However, technical losses have been reduced by 10 GWh compared to 2019.

CGES said that the average price of electricity supply to cover losses on an annual basis was 55.4 euros/MWh, 51.49 euros/MWh in March, when it was lowest, to 57.35 euros/MWh hour in January, when it was highest. Losses in the transmission system last year amounted to 163.6 GWh and were higher in nominal terms and lower in percentage compared to 2019. Losses in the transmission system last year were 1.82 % of total energy, while in 2019 they amounted to 146.5 GWh, which was 2.13 % at the time. Electricity supply contracts for last year were signed with four suppliers: EPCG, EFT, ALPIQ and GEN-I. The value of the contract, i.e. the costs of purchasing electricity to cover losses in the transmission system of Montenegro for last year amounted to 9.22 million euros.

When it comes to CEDIS, losses in 2020 amounted to 328.85 GWh, which is 12.93 % of total consumption in Montenegro. Losses in 2019 amounted to 356 GWh, which was 13.1 % at the time. In 2020, cost of electricity losses in the distribution system amounted to 12.05 million euros.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

Gvozd II wind expansion set for spring 2027 as EPCG complex reaches 76 MW

Montenegro is targeting spring 2027 for the commissioning of Gvozd II, as state utility EPCG expands its wind portfolio. The project is expected to bring the overall Gvozd complex to 76 MW. Construction activity is progressing on one of...

Montenegro extends Sinjajevina wind project timeline to 2030

Montenegro has extended the development timetable for the 112 MW Sinjajevina I wind farm, moving the expected commercial operation target toward 2030. The revised schedule reflects ongoing permitting and grid infrastructure constraints. The project is located near Kolašin. Government annex...

Montenegro imports nearly 30% of 2025 electricity as renewables dominate output

Montenegro relied on imports for almost 30% of its electricity needs in 2025. The country covered almost 30% of its electricity requirements through net imports, indicating ongoing exposure to regional wholesale markets. Domestic generation remained largely renewable during the...