Montenegro: HPP Perucica will be back online on September 15

Montenegrin power utility EPCG announces that the overhaul of hydropower plant Perucica is complete and the HPP is ready to return into operation on September 1, but the downtime will be extended until September 15.

This is due to a request from the regional waterworks company. It was requested that HPP Perucica remain out of operation until September 15 to keep the water flow in the Moraca river at its lowest level and ensure the measurement of water level parameters as part of the construction of a temporary embankment.

Taking into account the country’s energy balance and EPCG’s position in September, and considering society’s interest in resolving the water supply issue, a decision has been made to postpone the start of operations for HPP Perucica until September 15.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

World Bank-backed €50 million programme targets district heating in Pljevlja

Pljevlja transition programme and heating measures Montenegro is preparing an approximately €50 million World Bank-backed investment programme for Pljevlja. The effort targets district heating, cleaner household energy and efficiency measures as the country begins building infrastructure for an eventual transition...

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...
Supported byVirtu Energy