Supported byClarion Energy
HomeSEE Energy NewsMontenegro: Coal-fired TPP...

Montenegro: Coal-fired TPP Pljevlja’s operational hours can’t be extended

Last month, the Ministry for Capital Investments announced that it is in talks with the European Commission on obtaining additional working hours for TPP Pljevlja.

The Energy Community (EnC) Secretariat cannot extend the period of operation of coal-fired thermal power plant Pljevlja in the opt-out mode, which implies an exemption from compliance with the emission limit values, after the plant used its allowed 20,000 operational hours.

The Secretariat states that the number of working hours for the operation in that regime is defined by the Directive on Large Combustion Plants and the corresponding decision of the Council of Ministers. Any change could only be approved by the Council of Ministers, based on the proposal of the European Commission. The Secretariat may not extend the opt-out period and given the confirmation that the rules on work in that regime have not been respected, the Secretariat is currently preparing procedures for resolving disputes against Montenegro. At the end of 2020, TPP Pljevlja used 20,000 operational hours in opt-out mode, which it was supposed to spend in the period from 2018 to the end of 2023, and after that to start the process of environmentally-oriented reconstruction. For those 20,000 operational hours, the plant was exempted from the obligation to comply with the emission limit values.

The Secretariat believes that TPP Pljevlja reached the end of its allowed operation in the opt-out mode by the end of last year. The EnC contracting parties were to submit data on large installations, including the number of working hours, by 31 March 2021, on the basis of which the Secretariat would further decide on the actions to be taken. The Secretariat noted that after the expiration of 20,000 hours, the plant can remain in operation only if it meets the strict standards of the Industrial Emissions Directive. In order to achieve this goal, the reconstruction of the plant is inevitable.

 

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

World Bank-backed €50 million programme targets district heating in Pljevlja

Pljevlja transition programme and heating measures Montenegro is preparing an approximately €50 million World Bank-backed investment programme for Pljevlja. The effort targets district heating, cleaner household energy and efficiency measures as the country begins building infrastructure for an eventual transition...

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...
Supported byVirtu Energy