Montenegro: A tender for the construction of a transmission line worth 1.6 million euros has been launched

The Directorate for Capital Projects of Montenegro has announced a tender for the construction of electric power infrastructure for the electricity supply of the Cmiljača complex. It is a 35 kV transmission line, from the substation (TS) 110/35 KV Ribarevina to TS 35/10 KV Cmiljača.

For this tender, EUR 1.35 million without VAT, or EUR 1.63 million with VAT, has been determined.

The deadline for the completion of the works is six months from the introduction of the contractor into the work.

Offers can be submitted until May 8.

Supported byClarion Owners Engineers
Supported byspot_img
Supported byspot_img

Latest News

Supported byspot_img
Supported bySEE Energy News

Related News

EPCG completes major works on €26m Gvozd 2 wind expansion in Montenegro

Montenegro’s state power utility EPCG has completed most work on the second of three turbine foundations at its 21 MW Gvozd 2 wind project, advancing a nearly €26 million expansion further into construction. The project is located on the...

Perućica hydropower unit EPCG returns 190 MW after annual maintenance

Montenegro’s state power utility EPCG has returned 190 MW of capacity at the Perućica hydropower plant to operation after completing the main phase of its annual maintenance programme. The restoration brings additional generation capacity back online following the maintenance...

Montenegro’s renewable boom reaches the grid-connection test

Montenegro has accumulated a large pipeline of proposed solar and wind projects, but August reinforced that the decisive development constraint is shifting toward the transmission system. CGES and Nu Energy signed the grid-connection agreement for the Velestovo project, one of the country’s more advanced...
Supported byVirtu Energy